Assignment 1: Project management
Due: Mon Oct 4 in class.
As the head chef at Junior’s Restaurant, you created the following list of tasks needed to make an onion omelette:
- Beat eggs (takes 1 minute)
- Rinse vegetables (takes 2 min)
- Chop parsley (takes 1 min, depends on task 2)
- Chop onions (takes 2 min, depends on 2)
- Cook eggs and onions in pan (takes 3 min, depends on 1 and 4)
- Fold omelette in half, cook (takes 1 minute, depends on 5)
- Arrange on plate, garnish with parsley (takes 1 minute, depends on 3 and 6)
- Clean pan and utensils (takes 3 minutes, depends on 6)
Answer all of the following questions.
-
Draw a dependency graph to represent this project.
-
Assuming your kitchen is fully staffed (as many cooks as you could possibly need), how long will it take to prepare the omelette and clean up afterwards?
-
What is the critical path?
-
One of the cooks in your kitchen is new on the job. Which tasks would you assign him to ensure that he doesn't hold things up?
-
If you are short-staffed and need to do all these tasks yourself (one at a time), then how long will it take?
|